August 1999
|
Award of refloat contract
|
October 1999
|
DTI grants Consent for Cessation of Production (COP) from
Maureen
|
Q4 1999
|
Stakeholder consultation process begins
|
November 1999
|
The Moira subsea wellhead was removed from the seabed
|
December 1999
|
Commence platform decommissioning activities
(Progress Report - March 2000)
|
22nd December 1999
|
Refloat date revised to 2001
|
December 1999
|
Contract awarded to the PACT consortium to plug and abandon
Maureen wells (Progress Report - February 2000)
|
April 2000
|
Maureen Abandonment Safety Case
|
June 2000
|
Platform decommissioning activities
(Progress Report - June 2000)
|
December 2000
|
December 2000 Maureen Decommissioning Programme
Approved
The Secretary of State for Trade and Industry approved Phillips'
Decommissioning Programme for Maureen.
|
March 2001
|
March 2001 Maureen receives RoSPA President's Award for
Safety
|
March 2001
|
CSO Apache successfully recovers pipelines
|
25th June 2001
|
Maureen platform successfully refloated
|
30th June 2001
|
Maureen platform arrives at Stord, Norway
|
3rd July 2001
|
The Maureen loading column was successfully refloated at 1440
hours on 3rd July 2001 and towed to Stord in Norway where it is
now moored.
|
31st July 2001
|
Marine growth on the platform and loading column has now been
cleaned off the structures.
|
Sept/Oct 2001
|
Platform tank cleaning in progress.
|
16th October 2001
|
Phase 3 of the contract activated which allows the Maureen
Owners to exercise the option to deconstruct the Maureen
platform for re-use and recycling.
|
January 2002
|
Maureen Template Recovered and Seabed Cleared
|